May 26, 2007 - Day 339
The dumpsters have been removed, windows are in and the finishing touches are being completed on the third of the three major new additions to this renovated City high school - the Art Wing - shown in the banner photo above, over on the right.
Chatted with the building's custodian who was working on Saturday afternoon, first pic below. He thought the schedule was going to be really tight getting everything situated for opening day in September.
Chatted with the building's custodian who was working on Saturday afternoon, first pic below. He thought the schedule was going to be really tight getting everything situated for opening day in September.
See BAVPA Reconstruction Archive for additional details and updates.