June 9, 2007 - Day 353
Last Night at CEPA was able to see renderings of all the new schools. Will be posting about that shortly. Meanwhile here's the weekly fixBuffalo roof shot of the progress at Performing Arts. Noticed that some of the landscaping is being roughed in this week.
A few conversations with Paul McDonnell - the Board of Education's architect for this project - revealed that additional funding is being sought for the tennis courts. These were originally part of the project and were ruled out recently as cost over-runs on the hvac system were higher than expected.